Energy, Natural Resources and Infrastructure
June 02 2025

Vietnam MOIT decisions on Tariff Ceilings for LNG Power Plants and for Wind Power Plants of 2025

Combined-cycle gas turbine power plants using liquefied natural gas (LNG)

On 13 May 2025, the Ministry of Industry and Trade (“MOIT”) issued Decision No. 1313/QD-BCT (“Decision 1313”), which took immediate effect.

Decision 1313 sets a tariff ceiling of VND 3,327.42 per kWh (excluding VAT) for electricity generated by combined-cycle gas turbine power plants using LNG in 2025.

Wind Power Plants

On 30 May 2025, the MOIT issued Decision No. 1508/QD-BCT (“Decision 1508”), also with immediate effect.

Decision 1508 establishes a tariff ceiling of VND 1,987.4 per kWh (excluding VAT) for electricity generated by onshore and nearshore wind power plants in 2025.

The information provided here is for information purposes only and is not intended to constitute legal advice. Legal advice should be obtained from qualified legal counsel for all specific situations.